Dates
Received Date
Monday, February 25, 2019
Deadline to Request Public Hearing
Thursday, March 14, 2019
Deadline for Written Comment
Wednesday, April 10, 2019
Details
Project approved 7-0 at April 30, 2019 Review Board meeting.
- Application 2/25/2019
- Replacement Pages for Application 2/27/2019
- Certificate of Good Standing & Additional Information 3/4/2019
- Patients by Zip Code 3/4/2019
- Request for Expedited review 3/18/2019
- Revised Cost Space Information 3/18/2019
- Flood Plain Attestation Statement 3/18/2019
- Organizational Chart 3/18/2019
- Historic Preservation Letter 3/28/2019
- State Board Staff Report - April 2019 meeting 4/16/2019
- Additional Information 5/6/2019
- Permit Approval Letter 5/8/2019
- Notice of Requirement for Annual Progress Report 2/4/2020
- Notification of Operational Beds 2/20/2020
- Annual Progress Report 4/6/2020
- Notice of Project Completion 6/18/2020
- Additional Information 6/25/2020