Type A Modification received May 14, 2018.
Project Received Intent-to-Deny Ruling 4-1 - October 30 2018 Review Board meeting
Project approved 6-0 at June 4 Review Board meeting.
Permit renewal approved by State Board September 14, 2021
Permit Renewal was approved 8-0 at the December 14 2021 State Board Meeting
- Application 1/11/2018
- Updated Application Pages 2/7/2018
- Support Letters - Drs. Poley & Wessel, Retina Institute of Illinois 5/1/2018
- Modification of Project 5/14/2018
- Letter Concerning Type A Modification 5/15/2018
- Comments on Board Staff Report - Applicant 7/11/2018
- Board Staff Report July 24, 2018 - Corrected
- Additional Information 8/2/2018
- Additional Information 8/14/2018
- State Board Staff Report - October 30, 2018 - Establish ASTC
- Intention to Appeal Intent-to-Deny 11/9/2018
- State Board Staff Report 1/15/2019
- Request for Deferral 1/14/2019
- Affirmation of Deferral 1/14/2019
- State Board Staff Report - March 5, 2019, 2/19/2019
- Request to Defer Project 2/20/2019
- Confirmation of Deferral 2/25/2019
- State Board Staff Report - April 2019 meeting 4/16/2019
- Request to Defer Project 4/25/2019
- Project Deferral Letter 4/25/2019
- Additional Information 5/16/2019
- State Board Staff Report - June 4, 2019, Board Meeting 5/21/2019
- Permit Approval Letter 6/6/2019
- Notice of Requirement for Annual Progress Report 2/13/2020
- Permit Renewal Request 5/13/2020
- Permit Renewal Approval Letter 5/21/2020
- Annual Progress Report 6/2/2020
- Receipt of Annual Progress Report 6/3/2020
- Notice of Requirement for Annual Progress Report 4/6/2021
- State Board Staff Report - Permit Renewal 7/13/2021
- State Board Staff Report - Renewal 9/14/2021
- Permit Renewal Approval Letter 9/15/2021
- Board Staff Report - Permit Renewal - December 14, 2021
- Permit Renewal Approval Letter 12/14/2021
- State Board Staff Report - Permit Renewal 3/15/2022
- Notice of Project Completion
- Project Completion and Final Realized Cost Report