Dates
Received Date
Tuesday, April 12, 2016
- Project Received Intent to Deny 3-5-1 from Board July 23, 2012
Intent to Deny Letter
- Project Approved by Board 7-0-2 absent with conditions October 31, 2012
Permit Letter
Details
- Application
- Requested Information 5/7/2012
- Support Letters - Rep. Osmond & Sen. Duffy 6/22/2012
- Support Letter - Mayor of Zion 6/25/2012
- Support Letter - Gilda's Club 7/2/2012
- Additional Information 7/3/2012
- Requested Information 7/6/2012
- Page from Application 7/7/2012
- Comments on State Board Report - Cancer Treatment Centers 7/13/2012
- Intent to Deny Letter 7/25/2012
- Notice of Intent to Submit Additional Material 7/30/2012
- Supplemental Information 8/22/2012
- Memo on Technical Assistance 8/22/2012
- Type B Modification Request 10/5/2012
- Support Letter - Lake County Board 10/5/2012
- Permit Letter
- Resolution Approving Funds 11/26/2012
- Acknowledgement of Committment of Funds 11/27/2012
- Monthly Report 12/24/2012
- Confirmation of Compliance with Stipulation 12/26/2012
- Monthly Report 1/31/2013
- Monthly Report 3/29/2013
- Monthly Report 6/3/2013
- Confirmation of Compliance with Stipulation 6/3/2013
- Monthly Report 6/4/2013
- Letter Requesting Monthly Financial Statements 6/11/2013
- Monthly Bank Statement - March 2013 6/18/2013
- Monthly Bank Statement - January 2013 6/18/2013
- Monthly Bank Statement - May 2013 6/20/2013
- Notice Requiring Submittal of Monthly Financial Statement 7/30/2013
- Notice Requiring Submittal of Annual Progress Report 7/30/2013
- Monthly Financial Statement 7/31/2013
- Monthly Bank Statement for June 8/1/2013
- Monthly Bank Statement for July 8/14/2013
- Notice Requiring Annual Progress Report 8/29/2013
- Monthly Bank Statement for August 9/25/2013
- Monthly Bank Statement for September 10/22/2013
- Acknowledgment of Receipt of Information per Stipulation 10/22/2013
- Notice Requiring Final Realized Cost Report 10/28/2013
- Permit Renewal Request 11/15/2013
- Acknowledgment of Receipt of Information per Stipulation 11/22/2013
- Annual Progress Report 11/27/2013
- Monthly Bank Statement for October 11/27/2013
- Permit Renewal Approval Memo 12/10/2013
- Permit Renewal Approval Letter 12/11/2013
- Monthly Bank Statement for November 12/18/2013
- Acknowledgment of Receipt of Bank Statement 1/2/2014
- Notice Requiring Final Realized Cost Report 1/30/2014
- Monthly Bank Statement for December 2/20/2014
- Monthly Bank Statement for January 2/20/2014
- Notice of Project Completion 2/24/2014
- Monthly Bank Statement 2/28/2014
- Final Realized Cost Report 7/1/2014
- Acknowledgement of Project Completion 7/11/2014