Dates
Received Date
Friday, October 16, 2015
Details
Project Approved by Board 8-0-1 absent February 16, 2016
- Fresenius Annual Financial Report
- Application
- Support Letter - Mayor of Chicago Heights 11/25/2015
- Board Staff Report 2/2/2016
- Permit Approval Letter 2/17/2016
- Notice of Financial Committment 9/15/2016
- Receipt of Financial Committment 9/21/2016
- Notice Requiring Annual Progress Report 12/27/2016
- Annual Progress Report 2/8/2017
- Receipt of Annual Progress Report 2/9/2017
- Request for Permit Renewal 10/17/2017
- Renewal Approval Memo from Chair 10/31/2017
- Receipt of Annual Progress Report 2/28/2018
- Annual Progress Report 2/27/2018
- Final Cost Report 4/25/2018
- Receipt of Notice of Completion 4/26/2018