Dates
Received Date
Tuesday, September 06, 2016
Deadline to Request Public Hearing
Thursday, September 22, 2016
Deadline for Written Comment
Tuesday, February 28, 2017
Details
Project Approved at March 14, 2017 Review Board Meeting
- Application 9/6/2016
- Notice of Change of Corporation Name 9/9/2016
- Board Staff Report 1/10/2017
- Additional Information 2/10/2017
- Support Letter - State Rep. Beiser 2/14/2017
- Additional Information 2/14/2017
- Receipt of Support Letter - Rep. Beiser 2/14/2017
- Support Letter - Mayor of Granite City 2/21/2017
- Support Letter - Dan Simmons, President United Steelworkers Local 1899 2/21/2017
- State Board Report - March 14 2017 Meeting
- Permit Approval Letter 3/15/2017
- Removal of Patient Referrals - Dr. Cheema 10/18/2017
- Notice of Requirement for Annual Progress Report 1/30/2018
- Annual Progress Report and Financial Commitment 4/4/2018
- Receipt of Annual Progress Report 4/9/2018
- Request for Final Cost Report 5/31/2018
- Notice of Project Completion 6/27/2018
- Receipt of Notice of Completion 7/5/2018