Dates
Received Date
Thursday, August 17, 2017
Deadline to Request Public Hearing
Friday, September 01, 2017
Deadline for Written Comment
Wednesday, October 25, 2017
Details
Project Approved at November 14, 2017, Review Board Meeting.
Permit Renewal approved 5-0 at August 6, 2019 State Board Meeting.
Permit Alteration approved 5-0 at August 6, 2019 State Board Meeting.
- Application 8/17/2017
- Request for Public Hearing - City of Woodstock 8/24/2017
- Letter from Mercy Health Corporation 9/18/2017
- Request from State Rep. Reick 9/22/2017
- Oral Testimony at Public Hearing 10/2/2017
- Appearance at Public Hearing 10/2/2017
- Public Comment Public Hearing 10/2/2017
- Public Hearing Transcript 10/16/2017
- Letter from Dan Lawler in reponse to Letter from Mercy Health 10/25/2017
- State Board Report - November 14, 2017 - H-07
- Permit Approval Letter 11/21/2017
- Annual Progress Report 11/30/2018
- Receipt of Annual Progress Report 12/6/2018
- Notice of Requirement for Final Realized Cost Report 5/31/2019
- Request for Permit Renewal and Alteration 7/12/2019
- State Board Staff Report - August 6, 2019 meeting 7/23/2019
- State Board Staff Report - August 6, 2019 meeting 7/23/2019
- Permit Renewal Approval Letter 8/9/2019
- Permit Alteration Approval Letter 8/9/2019
- Project Completion and Final Cost Report 6/22/2020
- Receipt of Final Cost Report 6/22/2020