Dates
Received Date
Friday, January 12, 2018
Deadline to Request Public Hearing
Friday, February 02, 2018
Deadline for Written Comment
Wednesday, March 28, 2018
Details
Project Approved 6-0 at April 17, 2018, Review Board meeting.
- Application 1/12/2018
- Request for Expedited Review 1/26/2018
- Support Letter - State Rep. Bourne 2/5/2018
- Safety Net Impact Statement
- State Board Report - April 17, 2018
- Permit Approval Letter 4/19/2018
- Notice of Project Obligation 6/28/2018
- Receipt of Financial Commitment 6/29/2018
- Annual Progress Report 5/15/2019
- Receipt of Annual Progress Report 5/21/2019
- Notice of Requirement for Annual Progress Report 3/2/2020
- Annual Progress Report 6/5/2020
- Receipt of Annual Progress Report 6/8/2020
- Annual Progress Report
- Acknowledgement of Annual Progress Report
- Permit Renewal Request
- Approval Letter for Permit Renewal
- Annual Progress Report
- Acknowledgement of Annual Project Report
- Notice of Project Completion
- Audit of Project Costs
- Final Cost Report
Documents
Supplementary Information