Dates
Received Date
Wednesday, November 05, 2014
Details
Project Approved by Board 5-0-3 Absent March 10, 2015
Permit Renewal Approved 5-0 - October 30 2018 Review Board meeting
- Application
- Type A Modifcation Request 1/26/2015
- Letter Regarding Fee for Modification 1/28/2015
- Board Staff Report March 2015 14-056
- Permit Approval Letter
- Notice Requiring Annual Progress Report 1/28/2016
- Annual Progress Report 2/18/2016
- Request for Financial Committment Extension 2/18/2016
- Shell Space Attestation 2/18/2016
- Permit Renewal Request 2/18/2016
- Requested Information 2/19/2016
- Approval of Permit Renewal 3/2/2016
- Approval of Permit Alteration 3/2/2016
- Approval of Extension of Obligation 3/2/2016
- Notice of Requirement for Annual Progress Report 2/1/2017
- Annual Progress Report 3/10/2017
- Receipt of Annual Progress Report 3/15/2017
- Notice of Financial Committment 6/5/2017
- Change in Financing 12/13/2017
- Receipt of Alteration Information 12/15/2017
- Replacement MRI 1/23/2018
- Notice of Requirement for Annual Progress Report 1/30/2018
- Annual Progress Report 2/26/2018
- Receipt of Annual Progress Report 2/28/2018
- Notice of Change in Financing 9/10/2018
- Receipt of Change in Financing 9/21/2018
- State Board Staff Report - October 30, 2018 - Permit Renewal
- Permit Renewal Approval 11/5/2018
- Annual Progress Report 3/4/2019
- Noitce of Completion & Final Realized Cost Report 6/6/2019
- Receipt of Final Cost Report 6/7/2019