Dates
Received Date
Wednesday, February 13, 2013
Project Received Intent-to-Deny from Board 0-8-1 absent May 14, 2013
Project Approved by Board 6-1-1 absent September 24, 2013
Details
- Application
- Impact Letter - Palos Surgicenter 2/14/2013
- Opposition Letter 2/20/2013
- Impact Letter - Aiden Center for Day Surgery 2/25/2013
- Impact Letter - Oak Brook Surgical Centre 2/25/2013
- Opposition Letter - Oak Lawn Endoscopy 2/27/2013
- Requested Information 3/8/2013
- Correction of Referrals - Dr. Majmundar 3/15/2013
- Notice of Type B Modification 3/15/2013
- Additional Information 3/19/2013
- Additional Information 3/25/2013
- Additional Information 3/28/2013
- Additional Information 4/1/2013
- Physician Referral Letter - Dr. Bittar 4/9/2013
- Physician Referral Letter - Dr. Manglano 4/9/2013
- Impact Letter - Orland Park Surgical Center 4/15/2013
- Opposition Comments & Letter - Silver Cross Hospital 4/23/2013
- Support Letter - Preferred Surgicenter 4/24/2013
- Support Letter - Holland & Knight 4/24/2013
- Request to Appear and Submit Additional Information 5/22/2013
- Intent to Deny Letter 5/24/2013
- Technical Assistance Meeting 6/6/2013
- Request for Project Modification 7/15/2013
- Extension of Review Period 7/15/2013
- Opposition Letter - Palos Surgicenter 8/1/2013
- Support Letter - Rep. Zalewski 8/20/2013
- Opposition/Impact Letter - Palos Community Hospital 8/22/2013
- Support Letter 8/23/2013
- Support Letter - MPI Media Group 8/26/2013
- Support Letters 8/28/2013
- Support Letters 8/30/2013
- Support Letters 9/3/2013
- Support Letter - Sen. Hutchinson 9/4/2013
- Supporting Comments 9/4/2013
- Permit Approval Letter 10/8/2013
- Corrected Permit Approval Letter 10/15/2013
- Notice Requiring Annual Progress Report 7/29/2014
- Annual Progress Report 10/20/2014
- Notice of Project Completion and Final Realized Cost Report 2/18/2015
- Request for Notarized Attestation 2/25/2015
- Notice of Project Completion and Final Realized Cost Report 3/9/2015
- Notice Requiring Annual Progress Report 7/29/2015
- Annual Progress Report 9/16/2015
- Receipt of Annual Progress Report 9/16/2015
- Receipt of Final Realized Cost Report 11/24/2015