Dates
Received Date
Tuesday, August 20, 2013
Details
Project Approved by Board 8-0-1 absent w/stipulation December 17, 2013
- Application
- Requested Information 8/28/2013
- Requested Information 11/19/2013
- Support Letter 11/26/2013
- Comments - Fresenius 11/26/2013
- Support Letter - NxStage St. Louis 11/27/2013
- Opposition Letters - DaVita & Rockford Nephrology Associates 11/27/2013
- Support Letter - Dr. Kraus 12/2/2013
- Permit Approval Letter 12/19/2013
- Notice Requiring Final Realized Cost Report 7/29/2014
- Final Realized Cost Report 12/10/2014
- Final Realized Cost Report 12/23/2014
- Letter Acknowledging Project Completion 12/30/2014
- Request for Information 7/24/2017
- Requested Information 8/7/2017
- EMail from John Lawrence, NxStage 8/10/2017