Dates
Received Date
Friday, February 14, 2014
- Application
- Public Hearing Request 3/3/2014
- Petition of Support 3/31/2014
- Public Hearing Report 3/31/2014
- Public Hearing Report and Written Testimony 3/31/2014
- Public Hearing Transcript 3/31/2014
- Support Letter - Rep. Demmer 4/8/2014
- Support Letter 4/18/2014
- Financial Committment Letter 5/2/2014
- Permit Approval Letter
- Notice Requiring Annual Progress Report 4/29/2015
- Annual Progress Report 7/6/2015
- Acknowledgment of Receipt of Annual Progress Report 7/8/2015
- Annual Progress Report 8/3/2016
- Request for Alteration 8/3/2016
- Letter Regarding Request for Alteration 8/5/2016
- Receipt of Annual Progress Report 8/5/2016
- Notice Requiring Final Realized Cost Report 12/27/2016
- Notice of Completion 3/9/2017
- Notice of Requirement of Annual Progress Report 4/27/2017
- Final Realized Cost Report/Consent Agreement 5/24/2017
- Notice Requiring Annual Progress Report 4/30/2018
- Notice of Required Annual Progress Report 2/28/2019