Dates
Received Date
Monday, December 10, 2018
Deadline to Request Public Hearing
Thursday, December 27, 2018
Deadline for Written Comment
Wednesday, October 02, 2019
Details
Project received Intent-to-deny ruling 4-1 at March 5, 2019 Review Board meeting.
Project was approved 5-0 at October 22, 2019 State Board meeting.
Permit relinquished effective February 10, 2021.
- Application 12/10/2018
- Support Letter - State Rep. John D'Amico 2/5/2019
- Support Letter - Alderman Laurino 2/7/2019
- Support Letter - U.S. Sen. Durbin 2/11/2019
- Support Letters 2/14/2019
- State Board Staff Report - March 5 2019 2/19/2019 Correction
- Intent-to-Deny Letter 3/7/2019
- Request to Appeal Intent-to-Deny 3/8/2019
- Additional Information 4/17/2019
- State Board Staff Report - June 4, 2019 Board Meeting 5/21/2019
- Notice of Project Deferral 5/21/2019
- Request for Deferral 5/23/2019
- Request for Deferral 7/12/2019
- Confirmation of Deferral 7/12/2019
- Opposition Letter - Center for Renal Replacement 8/6/2019
- State Board Staff Report - October 22 2019 Board meeting
- Opposition Letter - Nephron Dialysis Center 10/21/2019
- Request to Relinquish Permit 2/8/2021
- Approval of Permit Relinquishment 2/10/2021