Dates
Received Date
Friday, April 26, 2019
Deadline to Request Public Hearing
Thursday, July 11, 2019
Deadline for Written Comment
Wednesday, July 17, 2019
Details
Application was modified June 26, 2019.
Project tentatively scheduled for August 6, 2019, State Board meeting.
Project approved 5-0 at August 6, 2019 State Board meeting.
- Application 4/26/2019
- Modified Application Page 6/26/2019
- Additional Information 6/27/2019
- Additional Information 6/27/2019
- State Board Staff Report - August 6, 2019 meeting 7/23/2019
- Permit Approval Letter 8/9/2019
- Request for Permit Renewal 5/21/2020
- Email Approving Permit Renewal 6/10/2020
- Permit Renewal Approval Letter 6/10/2020
- Final Realized Cost Report 2/10/2021
- Receipt of Final Realized Cost Report 2/11/2021