Dates
Received Date
Monday, May 01, 2017
Deadline to Request Public Hearing
Friday, May 19, 2017
Details
Project approved by Board Chairwoman July 28, 2017
Project Renewal approved by Review Board at January 15, 2019 meeting.
Project Alteration approved by Review Board at January 15, 2019 meeting.
- Application 5/1/2017
- Request for Expedited Review 5/5/2017
- Illinois Historic Preservation Agency Letter 5/11/2017
- Additional Information 7/25/2017
- Approval Memorandum 7/28/2017
- Permit Approval Letter 8/1/2017
- Notice of Financial Commitment 3/21/2018
- Receipt of Notice of Financial Commitment 3/23/2018
- Staff Report for Board
- Notice Requiring Annual Progress Report 5/31/2018
- Annual Progress Report 8/28/2018
- Notice of FInancial Commitment 9/21/2018
- Request for Renewal and Alteration 12/7/2018
- State Board Staff Report - Permit Renewal 1/15/2019
- State Board Staff Report - Permit Alteration 1/15/2019
- Approval of Renewal 1/17/2019
- Approval of Alteration 1/17/2019
- Notice of Requirement for Annual Progress Report 9/9/2019
- Final Cost Report 10/3/2019
- Receipt of Final Cost Report 10/8/2019