Dates
Received Date
Wednesday, December 21, 2016
Deadline to Request Public Hearing
Friday, January 13, 2017
Deadline for Written Comment
Wednesday, February 22, 2017
Details
Project Approved at March 14, 2017 Review Board Meeting
Permit renewal approved 5-0 at March 5, 2019 Review Board meeting
- Application 12/21/2016
- Additional Information 12/28/2016
- Application Attachment 7 2/14/2017
- Additional Information 2/15/2017
- State Board Report - March 14 2017 Meeting
- Permit Approval Letter 3/15/2017
- Alteration Request 5/2/2017
- Acknowlegdment of Decrease in Gross Square Footage 5/3/2017
- Notice of Requirement for Annual Progress Report 1/30/2018
- Annual Progress Report 4/4/2018
- Receipt of Annual Progress Report 4/9/2018
- Request for Permit Renewal 2/8/2019
- Financial Commitment Letter 2/11/2019
- Receipt of Financial Commitment 2/14/2019
- State Board Staff Report - March 5 2019 - Permit Renewal 2/19/2019
- Renewal Approval Letter 3/7/2019
- Annual Progress Report 3/7/2019
- Final Cost Report 10/9/2019
- Receipt of Final Cost Report 10/9/2019