Dates
Received Date
Wednesday, November 14, 2012
- Application
- Request for Expedited Review 11/20/2012
- Letters Regarding Bond Financing 1/16/2013
- Permit Approval Letter 2/14/2013
- Requested Information 4/11/2013
- Annual Progress Report and Final Cost Report 6/20/2013
- Notice Requiring Submittal of Annual Progess Report 12/26/2013
- Annual Progess Report 1/30/2014
- Notice Requiring Submission of Annual Progress Report 12/23/2014
- Annual Progress Report 1/29/2015
- Notice Requiring Submission of Annual Progress Report 12/30/2015
- Annual Progress Report 2/5/2016
- Notice Requiring Annual Progress Report 12/27/2016
- Notice of Requirement for Final Cost Report 2/1/2017
- Annual Progress Report 3/3/2017
- Receipt of Annual Progress Report 3/7/2017
- Notice of Project Completion 3/30/2017
- Permit Renewal Request 6/19/2017
- Chairwoman Approval 7/14/2017
- Renewal Approval Letter 7/17/2017
- Notice Requiring Final Cost Report 9/11/2017
- Final Realized Cost Report 10/30/2017
- Receipt of Notice of Completion 11/3/2017