Dates
Received Date
Monday, March 18, 2013
- Support Letter 3/1/2013
- Support Letter 3/7/2013
- Support Letter - Kane County Chairman 3/11/2013
- Application
- Permit Letter 6/27/2013
- Notice Requiring Annual Progress Report 4/28/2014
- Annual Progress Report 6/24/2014
- Notice of Project Obligation 2/17/2015
- Letter Acknowledging Project Obligation 2/18/2015
- Notice Requiring Annual Progress Report 4/29/2015
- Corrected Permit Letter 4/29/2015
- Annual Progress Report 7/14/2015
- Permit Alteration Request 7/14/2015
- Acknowledgment of Receipt of Annual Progress Report 7/15/2015
- Alteration Approval Memo 8/25/2015
- Alteration Approval Letter 8/26/2015
- Notice Requiring Annual Progress Report 4/28/2016
- Notice Requiring Final Realized Cost Report 4/28/2016
- Permit Renewal Approval Letter 6/1/2016
- Receipt of Annual Progress Report 7/11/2016
- Annual Progress Report 7/11/2016
- Notice of Requirement of Annual Progress Report 4/27/2017
- Annual Progress Report 7/3/2017
- Receipt of Annual Progress Report 7/3/2017
- Notice Requiring Annual Progress Report 4/30/2018
- Notice Requiring Final Cost Report 4/30/2018
- Notice of Completion 6/29/2018
- Final Cost Report 9/27/2018
- Receipt of Final Cost Report 11/7/2018