Dates
Received Date
Tuesday, June 28, 2016
Deadline to Request Public Hearing
Tuesday, November 29, 2016
Deadline for Written Comment
Wednesday, January 04, 2017
Details
Modification of project was received November 14, 2016.
Requests for Public Hearing must be received by November 29, 2016.
Project approved 6-0-2 absent at January 24, 2017 Board Meeting
Permit Renewal Approved 5-0 - October 30 2018 Review Board meeting
- Application 6/28/2016
- Request for Expedited Review 6/30/2016
- Approval for Expedited Review 7/1/2016
- Notice of Loss of Project Site 10/12/2016
- Receipt of Notice of Lost Site 10/13/2016
- Type A Project Modification 11/14/2016
- Board Staff Report 1/10/2017
- Permit Approval Letter 1/25/2017
- Notice of Requirement for Annual Progress Report 11/28/2017
- Notice of Obligation 12/19/2017
- Acknowledgment of Commitment 12/21/2017
- Request for Permit Renewal 8/14/2018
- State Board Staff Report - October 30, 2018 - Permit Renewal
- Permit Renewal Approval 11/5/2018
- Annual Progress Report 2/13/2019
- Receipt of Annual Progress Report 2/21/2019
- Final Realized Cost Report 10/17/2019
- Receipt of Final Realized Cost Report 11/29/2019