Dates
Received Date
Friday, June 20, 2014
- Project Received Intent-to-Deny from Board 4-2-3 absent October 7, 2014
Intent-to-Deny Letter- Project Approved by Board 5-0-3 absent December 16, 2014
Permit Approval Letter
Details
- Application
- Board Staff Report October 2014 14-026
- Deferral of Project to December Board Meeting 10/15/2014
- Intent-to-Deny Letter
- Notice of Intent to Submit Additional Information 10/14/2014
- Support Letter - Alderman Foulkes 11/17/2014
- Supplemental Information 11/21/2014
- Board Staff Report December 2014 14-026
- Permit Approval Letter
- Notice of Project Obligation 5/4/2015
- Acknowledgment of Receipt of Notice of Project Obligation 5/4/2015
- Notice Requiring Annual Progress Report 10/30/2015
- Annual Progress Report 12/15/2015
- Receipt of Annual Progress Report 12/16/2015
- Request for Permit Renewal 5/3/2016
- Permit Renewal Approval Letter 5/17/2016
- Notice Requiring Annual Progress Report 10/28/2016
- Annual Progress Report 12/9/2016
- Receipt of Annual Progress Report 12/12/2016
- Final Realized Cost Report 7/18/2017
- Receipt of Final Realized Cost Report 7/19/2017
- Notice of Requirement for Final Realized Cost Report 7/27/2017