Dates
Received Date
Friday, June 26, 2015
- Application
- Requested Information 7/10/2015
- Revised Application Attachments 7/23/2015
- Letter to Jacob Axel 7/28/2015
- State Board Report - August 25 Board Meeting
- Permit Approval Letter 8/26/2015
- Notice of Obligation 4/21/2016
- Notice Requiring Annual Progress Report 6/28/2016
- Annual Progress Report 8/15/2016
- Receipt of Annual Progress Report 8/16/2016
- Requirement for Annual Progress Report 6/28/2017
- Receipt of Annual Progress Report 9/20/2017
- Annual Progress Report 9/21/2018
- Notice of Completion 1/25/2019
- Final Cost Report 3/29/2019
- Receipt of Final Cost Report 4/3/2019