Dates
Received Date
Monday, November 06, 2017
Deadline to Request Public Hearing
Monday, November 27, 2017
Deadline for Written Comment
Wednesday, May 16, 2018
Details
Project approved 7-0 at June 5 2018 Review Board meeting.
Permit renewal approved by Board Chairman February 14, 2020
- Application 11/6/2017
- Request for Expedited Review 11/8/2017
- Additional Information 3/2/2018
- Additional Information 3/20/2018
- State Board Report - June 5, 2018
- Permit Approval Letter 6/12/2018
- Amended Approval Letter 9/20/2018
- Notice of Required Annual Progress Report 2/28/2019
- Annual Progress Report 7/3/2019
- Recipt of Annual Progress Report 7/9/2019
- Request for Permit Renewal 2/10/2020
- Renewal Approval Memo 2/14/2020
- Permit Renewal Approval Letter 2/15/2020
- Notice of Address Change 4/29/2020
- Corrected Permit Letter 4/29/2020
- Annual Progress Report 6/29/2020
- Receipt of Annual Progress Report 6/29/2020
- State Board Staff Report - Permit Renewal 9/14/2021
- Permit Renewal Approval Letter 9/16/2021