Dates
Received Date
Thursday, May 30, 2013
- Project Received Intent-to-Deny from Board 3-5-1 absent September 24, 2013
Intent-to-Deny Letter- Project Approved by Board 8-0-1 absent December 17, 2013
Corrected Permit Approval Letter
Details
- Application
- Response to Staff Concerns 8/19/2013
- Notice of Intent to Submit Additional Information 10/1/2013
- Intent-to-Deny Letter 10/10/2013
- Modification of Application 10/15/2013
- Acknowledgment of Modification 10/21/2013
- Permit Approval Letter 12/19/2013
- Annual Progress Report 12/17/2014
- Corrected Permit Approval Letter
- Notice Requiring Annual Progress Report 10/30/2015
- Annual Progress Report and Project Obligation 12/29/2015
- Receipt of Annual Progress Report and Financial Committment 12/30/2015
- Request for Alteration 8/9/2016
- Requested Information 8/12/2016
- Alteration Approval Letter 8/22/2016
- Notice of Project Completion & Final Realized Cost Report 9/2/2016
- Receipt of Final Realized Cost Report 10/7/2016