Dates
Received Date
Thursday, February 18, 2016
Deadline to Request Public Hearing
Friday, March 04, 2016
Deadline for Written Comment
Wednesday, April 20, 2016
Details
Project Approved 6-0, 1 passed, 2 absent by Board at May 10, 2016 meeting
- Application
- Letter of Intent to Lease 3/2/2016
- Board Staff Report 4/26/2016
- Permit Approval Letter 5/11/2016
- Notice of Change of Corporation Name 9/9/2016
- Change in Contact Information 12/9/2016
- Notice Requiring Annual Progress Report 3/29/2017
- Annual Progress Report 6/9/2017
- Final Realized Cost Report 12/12/2017
- Receipt of Final Cost Report 12/13/2017