Dates
Received Date
Friday, April 25, 2014
- Application
- Permit Approval Letter
- Notice Requiring Annual Progress Report 5/28/2015
- Annual Progress Report 8/17/2015
- Notice of Obligation 9/11/2015
- Receipt of Financial Committment 9/11/2015
- Notice Requiring Annual Progress Report 5/27/2016
- Annual Progress Report 8/10/2016
- Notice Requiring Annual Progress Report 5/31/2017
- Annual Progress Report 8/11/2017
- Receipt of Annual Progress Report 8/14/2017
- Notice of Requirement for Final Cost Report 10/31/2017
- Notice of Completion/Request for Alteration 12/28/2017
- Permit Renewal Request 2/9/2018
- Receipt of Alteration Information 2/15/2018
- Renewal Approval Memorandum 2/26/2018
- Renewal Approval Letter 3/1/2018
- Notice Requiring Final Cost Report 4/30/2018
- Notice Requiring Annual Progress Report 5/31/2018
- Notice of Completion & Final Cost Report 6/8/2018
- Request for Additional Information 6/14/2018
- Audit Report 6/28/2018
- Receipt of Completion Notice 6/28/2018